ENGINEERING · ASSEMBLY · INSPECTION

Solar System Integration & Export Coordination

See how the equipment scope is checked from project brief through model selection, inspection and dispatch.

Solar System Integration & Export Coordination
ORDER WORKFLOW

A traceable path from brief to shipment.

Each order should state the exact production site, selected models and inspection deliverables.

01

Engineering review

Check load profile, site voltage, grid conditions and backup target.

02

Component matching

Confirm inverter, battery, PV, protection and communication compatibility.

03

Inspection plan

Agree on model documents, functional checks and packing evidence.

04

Export preparation

Match equipment labels, manuals, packing lists and trade documents.

Technician inspecting electrical equipment in a workshop
QUALITY RECORDS

Ask for evidence tied to the selected models.

Certificates, warranty terms and test records apply to particular products and configurations. The order file should show which documents support the equipment actually shipped.

  • Named bill of materials and product datasheets
  • Single-line diagram and interface description
  • Model-specific certificates where applicable
  • Inspection records and packing photographs

Visuals illustrate workshop and inspection activities; production site and test scope are confirmed per order.

PRODUCTION SEQUENCE

Five stages, each with a record

Every stage produces a document the next stage depends on. That is what makes the order traceable from the brief through to the packing list.

Production and inspection sequence
StageWhat is checkedRecord producedTypical duration
Engineering reviewLoad profile, site voltage, grid conditions, backup targetDesign basis and single-line diagram1 to 3 days
Component matchingInverter, battery, PV, protection and communication compatibilityNamed bill of materials1 to 2 weeks
AssemblyConfiguration against the approved BOMBuild record and configuration log1 to 3 weeks
72-hour testingFull-load functional test before shipmentTest record and inspection photographs72 hours
Export preparationLabels, manuals, packing lists, trade documentsPacking list and commercial documents2 to 6 weeks

Total programme runs 4 to 12 weeks. Durations are planning ranges, not commitments.

DOCUMENTATION

What should travel with the shipment

Certificates and test records apply to particular models and configurations. The order file should show which documents support the equipment actually shipped.

Order documentation
DocumentWhat it showsWhy it matters
Named bill of materialsExact model and electrical interfaceLets the buyer verify what was quoted against what was shipped
Single-line diagramProtection, distribution and interfacesThe reference the installer and inspector work from
Model-specific certificatesCE, IEC 62619, UN38.3, MSDS as applicableNeeded for customs and for grid interconnection review
Test and inspection recordsFunctional checks and 72-hour test resultEvidence the system was energised before it left
Packing photographs and listAs-packed condition of the shipmentThe basis for any transit claim

Documents are listed per order. Which certificates apply depends on the models and the destination.