SOLAR POWER SYSTEMS BATTERY STORAGE EXPORTContact Force Solar ↗

By Force Solar Engineering Team · Published 1 October 2026 · Updated 6 October 2026

INSTALLATION NOTES

How a 400 kW Rooftop Solar System Comes Together

A factory rooftop build in Butuan City, Philippines — from the first survey to the last row of panels.

Completed 400 kW rooftop solar array with maintenance walkway in Butuan City, Philippines

Short answer

A 400 kW rooftop system for a three-shift factory is built in four stages — site survey, mounting substructure, row-by-row panel installation, then commissioning and handover. On this Butuan City build the rails, clamps and maintenance walkway went down before a single panel, and the electrical crew worked in parallel with the roof crew. The order matters more than the speed: survey decisions set the mounting, and the mounting decides whether the array stays serviceable.

A three-shift factory runs on daytime electricity, which makes it a natural fit for rooftop solar. This 400 kW installation in Butuan City, Philippines was configured so that solar generation covers the production load while the grid stays connected as the balancing source.

The sequence below is the same one we follow on every export project: survey first, engineer second, install and commission last. Skipping ahead is how systems end up undersized, miswired or impossible to maintain.

Start with the site survey

Before any hardware is discussed, the roof has to answer practical questions: usable area, orientation, shading from nearby structures, the condition of the metal sheets, and where cables can run from the array to the inverter room.

For this factory, the survey also mapped a maintenance walkway. A 400 kW array covers a large area, and without planned access routes, cleaning and inspection become difficult within the first year.

Mounting rails and walkway sections installed on the metal factory roof
Mounting rails and walkway sections installed on the metal factory roof
Stages of a 400 kW rooftop build
StageWhat actually happensWhat it protects
Site surveyUsable area, orientation, shading, sheet condition, cable route to the inverter roomMounting design and planned access routes
Layout and mountingRails, clamps and walkway installed to the sheet profile and local wind loadStraight rows, accessible clamp points, serviceability
Panel installationPanels lifted, seated, clamped and wired in strings per the engineering drawingInverter MPPT windows and expected yield
Commissioning and handoverInsulation, polarity and string voltage tests, inverter start-up, monitoring configuredAs-built layout, bill of materials, component documentation

Sequence reflects Force Solar installation records for this project; export orders follow the same order with configuration records and inspection photos before shipment.

Layout and mounting come before panels

Rails, clamps and walkway sections go down first. On a metal roof, the mounting system has to match the sheet profile and the local wind load — this is specified per project, not assumed.

Getting the substructure right is what allows panel installation to move quickly later. Every row is straight, every clamp point is accessible, and the array stays serviceable.

Panel installation, row by row

With the mounting complete, crews work row by row: panels are lifted, seated, clamped and connected in strings. On this build the roof crew and the electrical crew worked in parallel — one finishing the array, the other preparing the inverter and protection panels.

String layout follows the engineering drawing exactly, because the inverter MPPT windows were calculated against those string lengths. Improvising on the roof is how yield gets lost.

Installation crew mounting solar panels row by row on the factory roof
Installation crew mounting solar panels row by row on the factory roof

Commissioning and handover

After electrical tests — insulation, polarity, string voltages, inverter start-up — the system goes live and monitoring is configured. The handover file includes the as-built layout, the bill of materials and the documentation for each major component.

For export projects, the same discipline applies before shipment: configuration records, inspection photos and packing lists travel with the order.

Photographs from Force Solar installation records. Figures describe the referenced project configuration; every new system is sized against its own load data.

START A PROJECT

Frequently asked questions

What happens first on a 400 kW rooftop project?

A site survey, before any hardware is discussed. It has to answer usable area, orientation, shading from nearby structures, the condition of the metal sheets, and where cables can run from the array to the inverter room. On this build the survey also mapped a maintenance walkway.

Why does the mounting go down before the panels?

Because the substructure decides whether the array stays serviceable. On a metal roof the rails, clamps and walkway have to match the sheet profile and the local wind load, which is specified per project rather than assumed. Getting it right is what lets panel installation move quickly later.

Can the roof crew and the electrical crew work in parallel?

Yes. That is how this build ran: one crew finished the array while the other prepared the inverter and protection panels. String layout still followed the engineering drawing exactly, because the inverter MPPT windows were calculated against those string lengths.

What is tested before the system goes live?

Insulation, polarity and string voltage tests, then inverter start-up and monitoring configuration. The handover file includes the as-built layout, the bill of materials and the documentation for each major component.

Is a three-shift factory a good fit for rooftop solar?

Yes. A three-shift factory runs on daytime electricity, which makes it a natural fit. This 400 kW system was configured so solar covers the production load while the grid stays connected as the balancing source.

What travels with an export order before shipment?

The same discipline applied at handover: configuration records, inspection photos and packing lists travel with the order.

Sizing a similar system?

Send the load details, outage pattern and destination — we will respond with the engineering inputs needed for a proposal.

Request a system proposal
WhatsApp+86 137 0282 0912